ABSTRACT
The enforcement of arbitral awards in Nigeria
raises important questions concerning the period within which enforcement
proceedings may be commenced. Before the Arbitration
and Mediation Act 2023, the Supreme
Court considered limitation in relation to arbitral awards in Murmansk State Steamship Line v Kano Oil
Millers Ltd and City Engineering (Nig) Ltd v Federal Housing Authority.
Those decisions treated the limitation issue by reference to the underlying
cause of action. The Arbitration and
Mediation Act 2023 has introduced a specific statutory provision dealing
with the computation of time for enforcement. Section 34(4) provides
that, in computing the time for commencing proceedings to enforce an arbitral
award, the period between the commencement of arbitration and the date of the
award shall be excluded. This article examines the earlier judicial position
and the effect of the statutory provision. It also distinguishes statutory
limitation from the equitable concept of laches and considers whether delay
after an award has been made constitutes an independent basis for resisting
enforcement. The article argues that section
34(4) provides a clear statutory rule concerning the period spent in
arbitration, while the legal effect of post-award delay must be determined by
the applicable limitation law and any other established legal rule. The article
does not treat laches as an established independent defence to enforcement
where no direct Nigerian authority has been identified establishing such a
proposition.
Keywords:
Arbitration; Arbitral Awards; Enforcement; Limitation;
Delay; Laches.